Hours: Target vs. Actual Comparison

Now we "just" need the option to enter the total hours (e.g., 1,200 h) under "Projects" and, if necessary, the option to enter the "remaining hours" for the project under "Reports." So, if two people worked 8 hours a day for two weeks, my example would result in:

Total hours for Project 4711: 1,200 h

Employee Müller: 10 days * 8 hours -80 hours

Employee Meier: 10 days * 8 hours -80 hours

--------------------------------------------------------------

Remaining hours : 1,040 h

We have construction sites that run for over 4 months, and in some cases even over 1.5 years. For the site manager, this feature is extremely important for seeing at a glance how construction progress compares to the budget.

Of course, it should be possible to adjust the total hours (e.g., due to change orders),

and a “reminder” (e.g., “You have reached 50% of the planned hours,” “You are currently using more hours than calculated”) would also be helpful.